Which Warehouse Automation Decisions Should Travel From Site to Site?

A team that spends most of its shift picking small electrical components has a different problem from one cutting cable to length. Both might need automation. Only one needs a system built around moving large numbers of small items to fixed workstations. The challenge for a distributor with both kinds of work is deciding how much of the first successful installation to repeat.
Jérémie Profeta, chief transformation officer at Sonepar, drew that line in written answers. Small parts account for 60–70% of order lines, he said, making high-density storage and goods-to-person picking a strong fit. Cable cutting calls for a different approach. The company says it added five automated distribution centers in 2026, bringing its count to 42.

Copy the Tests, Then Pick the Equipment
“What we want to replicate is a proven way of working,” Profeta said. His team standardizes how sites make the business case, choose suppliers, run tests and train operators. A reference design gives a site somewhere to start. Local teams adapt it to the order mix, the building and the level of service customers expect.
That distinction matters when a site goes live. Equipment can hit a picking target while orders pile up before packing. An acceptance test worth repeating would follow orders through dispatch and include exceptions the local team actually sees. Sites could run the same test with different products and layouts, then compare where work gets held up.
Decide What to Change When Demand Moves
In earlier Supply Chainer coverage, Stanislas Normand, managing director of Exotec North America, said, “Storage capacity and throughput can easily be decoupled.” More storage may solve an inventory problem. A slowdown at a picking station needs a different response. A rollout that tests those constraints separately gives the local manager a reason to change the design when the order mix shifts.
Profeta said Sonepar raises activity as the site proves stable. That makes the first sustained run at a higher volume a test of the design and the crew. The team can see where exceptions collect and whether staff can clear them before orders miss their deadlines. The next warehouse can inherit those checks even if it buys different equipment.